B&Q
Facts and figures
- Average store 3-10 weeks
- £16.5m
Interserve’s 90-week programme, awarded by Thornfield Properties Plc, involved extensive demolition and asbestos removal works and significant ground remediation. The existing major services had to be diverted and a substantial remodelling exercise of the main arterial roundabout in Chesterfield was carried out.
Sustainable design and build
Additionally, Interserve provided the design and build of a commercial office development and a Stretch B&Q superstore – a total of 10,000 sq m of principle sales floor. The external works include extensive remodelling and the creation of an urban park, with woodland walks and a skate board park. Interserve also built 650 external parking bays.
Services
- Demolition
- Civils
- Design and build
Achievements
- Sustainability features include:
- 95 per cent of all material maintained on site
- Replace deep drainage with innovative use of shallow Sustainable Urban Drainage System (SUDS)
- Rainwater harvesting
- Demolition material reclaimed and strengthened to form granular CBM road foundation
- Solar heating
- Bio-remediation of hydro carbon contaminated soils—material remained on site
- Certainty of delivery
- Early integration of fit-out works
- Robust commercial control
- Ownership of delivery resting with the contractor
- Winner of Building Regional Services Safety Award
- Existing weak strata modified with quicklime to form structural fill — mitigated importing